Re: Reminder: Never connect a generator to home wiring without transfer switch


From: Herb L <herbleong () gmail com>
Date: Mon, 30 Aug 2021 09:20:11 -0700

https://www.csemag.com/articles/grounding-points-single-or-multi/

On Aug 30, 2021, at 09:10, Mark Tinka <mark@tinka.africa> wrote:



On 8/30/21 17:59, Aaron C. de Bruyn via NANOG wrote:


Would you care to educate me on this?
If you ground the phases on both sides of the work-site, how are you going to end up being a better path to ground?

I'm not sure if it applies to work sites for linesmen, but my limited understanding is that you don't generally want 
to ground at more than one point.