For what it's worth, was part of a datacenter operations department
that
had a 24x7 team. 4 shifts, 4 staff on each shift (1 was supervisor who
did same work as the rest, 1 'point of contact' who stayed in the
office).
4 days on, 4 days off, 12 hour shifts, 8-8. Shift teams would
alternate
between day and night (so 4 day, 4 off, 4 night, 4 off, repeat ad
infinitum). During the day that was bolstered by 6 day-staff, Monday
to
Friday, who would have a staggered start through the day (IIRC 2 start
at 8, 2 at 9, 2 at 11)

And also for what it's worth, my understanding of body circadian rhythm
research suggests that "every 8 days" is *WAY* too short a period to
be flipping people's shifts from day to night; every 6 months is more
reasonable.